PROJECT COSTS
January 12, 1997
Estimated Project Costs
19th and Rollandet
|
Removal Items |
Estimated Itemized Cost |
|
Remove Curb & Gutter - 626 Lineal Feet (L.F.) @ $2.00 per L.F. = |
$1,252.00 |
|
Remove Asphalt Pavement - 1528 Square Yards (S.Y.) @ $3.00 per S.Y. = |
$4,584.00 |
|
Street Excavation - 1,350 Cubic Yards (C.Y.) @ $6.00 per C.Y. = |
$8,100.00 |
|
Construction Items |
Estimated Itemized Cost |
|
Concrete Curb & Gutter - 626 L.F. @ $12.00 L.F. = |
$7,512.00 |
|
Granular Borrow - 900 C.Y. @ $7.00 C.Y. = |
$6,300.00 |
|
4" of Asphalt Pavement over 10" of 3/4" Crushed Gravel Base - 1,528 S.Y. @ $8.25 per S.Y. = |
$12,606.00 |
|
5' Wide Concrete Sidewalk, 4" thick - 342 S.Y. @ $20.00/S.Y. = |
$6,840.00 |
|
Seal Coat - 1,528 S.Y. @ $1.00 S.Y. = |
$1,528.00 |
|
TOTAL (EXCEEDS $25,000! see item 5. below) |
$48,722.00 |
NOTE: Cost does not include 6" thick concrete Commercial Driveways or Asphalt Tack Coat, Storm Drainage System, etc.
Senate Bill No. 1113
Revised Bid Limits Association of Idaho Cities
April 1995 Budget Workshop
Item 5.) Competitive bids -
"When expenditure exceeds
$25,000 it shall
be contracted for and let to the lowest
responsible bidder."
Also See Idaho Code Section 54-1218 Public Work